Skip to content

Realistic Timeline — What Happens When

Most first-time business owners underestimate the timeline by 50–100%. This page lays out the realistic schedules for three common scenarios so you can plan backwards from your target opening day.


When you see… It means…
Critical path The sequence of tasks that determines the minimum project length. A delay on the critical path = a delay to opening day.
Float Slack time on tasks not on the critical path. Use it for scheduling flexibility.
Lead time How long an external item takes from order to delivery (kitchen hood, ABC permit, etc.).
CO (Certificate of Occupancy) The city document permitting you to operate. The doorway to opening day.
TI (Tenant Improvement) allowance Money the landlord contributes toward build-out — negotiated in the lease.

You’re moving into a space that was already used for the same kind of business as yours. Maybe a retail shop with new fixtures, paint, signage. No structural work, no plumbing changes, no use change.

Week Milestone On critical path? Notes
0 Sign lease
0–1 Confirm Change of Tenant requirements with city Free phone call to 910-433-1707
1–2 Submit Change of Tenant application via IDTplans
2–4 City review (typically 2–4 weeks for tenant change)
1–3 Order signage, fixtures (parallel with city review)
1–2 Apply for sign permit if changing signs Sign permit ~3–5 business days
1–4 Cosmetic work (paint, install fixtures) Can run in parallel with city review
4–5 Final inspection
5 Receive new Certificate of Occupancy
5–6 Open
6+ Hire/train staff if needed; soft launch

Realistic: 6–10 weeks lease-to-opening. Add 1–2 weeks for surprises (sign approval delays in Historic District, fixture shipping issues).


You’re moving into a space that needs interior walls built or removed, new finishes, maybe new electrical for your fixtures, but no kitchen and no change of use. Example: bookstore moving into a former clothing store.

Week Milestone Critical path? Notes
0 Sign LOI / lease
0–2 Hire architect or designer; verify GC license at nclbgc.org See Hiring a Build-Out Contractor
1–4 Architect produces drawings Cosmetic plans: 1–2 weeks; full layout: 3–4 weeks
4–6 Submit Change of Tenant + permit applications
6–10 City plan review 4–8 weeks typical for moderate scope
10–12 Address review comments, resubmit Usually 1–2 cycles
12 Permits issued
12–20 Construction (4–8 weeks for interior build-out)
4–18 Order long-lead items in parallel: signage, custom fixtures Start ordering during plan review, not construction
18–20 Rough-in inspections Electrical, framing
20 Final inspections
20–22 Receive Certificate of Occupancy
16–22 Hire staff, set up POS, marketing Parallel work in late stages
22 Open

Realistic: 5–6 months lease-to-opening. Historic District adds 2–4 weeks for COA review on any visible exterior changes.


You’re converting a space (often retail or office) into a restaurant with full kitchen, dining seating, and alcohol service. This is the most complex downtown scenario and the one most often miscalculated.

Week Milestone Critical path? Notes
0 Sign LOI / lease
0–2 Pre-submittal feasibility call to Development Services Critical — confirm what change-of-use will trigger before signing
2–4 Hire architect with restaurant experience; vet GCs
2–4 PWC service capacity review (3-phase power, water, sewer) Can take 4–8 weeks just for confirmation
4–10 Architectural drawings + MEP engineer Full restaurant: 6–8 weeks
4–6 Order kitchen hood (10–14 week lead time) Long lead — order before plans are even approved
4–6 Order kitchen equipment (8–12 week lead time on some items)
10–14 Submit Change of Use application + permits
14–22 City plan review (multi-discipline: building, fire, plumbing) 6–10 weeks for full restaurant scope
18–24 Address review comments, resubmit Often 2–3 cycles for restaurants
24 All permits issued
24–40 Construction (8–16 weeks)
24–36 Sub schedule: framing → MEP rough → drywall → finishes → equipment
36–40 Hood install + fire suppression + grease trap inspections
38–42 Health Department plan review and pre-opening inspection Cumberland County Health, 910-433-3600
40–42 Final building inspections
42 Certificate of Occupancy issued
42 NOW apply for ABC alcohol permit Cannot apply until CO; ABC takes 30–60 days
42–50 ABC review and approval
38–50 Hire kitchen staff, train, do soft openings Parallel work
50–52 Grand opening with alcohol service

Realistic: 10–12 months lease-to-opening for a full restaurant with alcohol. Push out to 12–14 months if the building has historic-district status, sprinkler retrofit, structural upgrades, or PWC service capacity issues.


The reason these timelines stack up is that critical-path items can’t be parallelized. Here’s the chain for a full restaurant:

Sign Lease
Pre-submittal call (1 day)
Architect/MEP drawings (6–8 weeks)
Submit permit application
Plan review (6–10 weeks, often 2–3 cycles)
Permits issued
Construction (8–16 weeks)
Final inspections
Certificate of Occupancy
├──→ Health Department final inspection
├──→ Fire Marshal final
└──→ ABC permit application (30–60 days)
Open with alcohol

What you can run in parallel (i.e., what’s not on the critical path and gives you “float”):

  • Long-lead equipment orders (start during plan review, not construction)
  • Sign permit application (can run alongside main permits)
  • Hiring and training staff (start mid-construction)
  • Marketing, branding, website, social media (anytime)
  • POS system setup (anytime)
  • Insurance procurement (before opening, not blocking)

Lessons from owners who missed their target dates:

Surprise How long it adds
Plan review comments require redesign 4–8 weeks per cycle, sometimes 2–3 cycles
Kitchen hood lead time 10–14 weeks (most common construction delay)
Grease trap or PWC service upsizing 4–12 weeks
Sprinkler retrofit triggered by Change of Use 6–12 weeks design + install
Historic Resources Commission review 30+ days (HRC meets monthly — miss the deadline, wait a month)
GC discovers hidden conditions during demo Variable — wood rot, asbestos, lead paint, electrical
ABC application backlog Can extend the standard 30–60 days
Health Department comment letter 2–4 weeks
Holiday season (Thanksgiving through New Year) Plan reviews and inspections slow during city holidays

Can I open earlier by working with a “permit expediter”? A reputable expediter can shave a few weeks off plan review by submitting clean packages and following up with reviewers. They cannot circumvent statutory review periods or skip steps. Expect to pay $2,000–$10,000 for expediting services, often money well-spent on a complex project.

My landlord says they can give me a CO from when the previous tenant occupied. Is that good enough? No. A CO is specific to the use that was approved at the time it was issued. Your new use needs a new CO. If a landlord tells you otherwise, get it in writing — and then verify with Development Services. The landlord may be honestly mistaken.

What’s the absolute earliest I can apply for an ABC permit? The day your Certificate of Occupancy is issued. ABC typically requires the CO and a copy of your fully executed lease as part of the application. Some preliminary paperwork (entity formation, background checks) can be prepared in advance to speed things up once CO arrives.

Should I sign a lease that starts before construction begins? Common practice is a “free rent period” (60–120 days) at lease start to give time for build-out before paying rent. Negotiate this. For a complex restaurant build-out, free-rent periods of 6+ months are not unreasonable. Without it, you’re paying rent on a space you can’t occupy.

Can I shorten the timeline by skipping the architect for cost reasons? For anything beyond cosmetic work, NC requires sealed drawings (architect or PE) for most non-trivial commercial projects. Skipping the architect usually means the city kicks the application back, costing more time than the architect’s fee would have. The right question is “which architect” — get one with restaurant or commercial-build-out experience.

What if I just want to “soft open” before I have everything done? You cannot legally operate without a Certificate of Occupancy. “Soft open” means inviting friends and family for a private event in a not-yet-permitted space, which is a code violation and an insurance disaster waiting to happen. Wait for CO.


Need Contact
Pre-submittal feasibility (does my space work for my use?) Development Services — 910-433-1707
PWC service capacity review PWC — 910-483-1382
Health Department restaurant pre-opening Cumberland County Health — 910-433-3600
ABC alcohol permits NC ABC Commission — 919-779-0700
Free 1:1 timeline planning FTCC Small Business Center — 910-678-8400
Downtown business advisor Downtown Development — 910-433-1599

See also: